ITCertMaster Microsoft 70-492 exam training materials have the best price value. Compared to many others training materials, ITCertMaster's Microsoft 70-492 exam training materials are the best. If you need IT exam training materials, if you do not choose ITCertMaster's Microsoft 70-492 exam training materials, you will regret forever. Select ITCertMaster's Microsoft 70-492 exam training materials, you will benefit from it last a lifetime.
Microsoft 070-346 is a certification exam to test IT professional knowledge. ITCertMaster is a website which can help you quickly pass the Microsoft certification 070-346 exams. Before the exam, you use pertinence training and test exercises and answers that we provide, and in a short time you'll have a lot of harvest.
ITCertMaster provide you the product with high quality and reliability. You can free download online part of ITCertMaster's providing practice questions and answers about the Microsoft certification 74-344 exam as a try. After your trail I believe you will be very satisfied with our product. Such a good product which can help you pass the exam successfully, what are you waiting for? Please add it to your shopping cart.
If you are interested in ITCertMaster's training program about Microsoft certification 070-346 exam, you can first on WWW.ITCertMaster.COM to free download part of the exercises and answers about Microsoft certification 070-346 exam as a free try. We will provide one year free update service for those customers who choose ITCertMaster's products.
Exam Code: 70-492
Exam Name: Upgrade your MCPD: Web Developer 4 to MCSD: Web Applications
Guaranteed success with practice guides, No help, Full refund!
Microsoft 70-492 Exam Cram 132 Q&As
Updated: 2014-08-24
70-492 Braindumps Detail : Click Here
Exam Code: 070-346
Exam Name: Managing Office 365 Identities and Requirements
Guaranteed success with practice guides, No help, Full refund!
Microsoft 070-346 Exam Cost 78 Q&As
Updated: 2014-08-24
070-346 Exam Tests Detail : Click Here
Exam Code: 74-344
Exam Name: Managing Programs and Projects with Project Server 2013
Guaranteed success with practice guides, No help, Full refund!
Microsoft 74-344 Braindumps 97 Q&As
Updated: 2014-08-24
74-344 Bootcamp Detail : Click Here
ITCertMaster has a huge IT industry elite team. They all have high authority in the IT area. They use professional knowledge and experience to provide training materials for people ready to participate in different IT certification exams. The accuracy rate of exam practice questions and answers provided by ITCertMaster is very high and they can 100% guarantee you pass the exam successfully for one time. Besides, we will provide you a free one-year update service.
Having a Microsoft certification 70-492 exam certificate can help people who are looking for a job get better employment opportunities in the IT field and will also pave the way for a successful IT career for them.
74-344 Free Demo Download: http://www.itcertmaster.com/74-344.html
NO.1 You are a program manager for a company that uses Project Server 2013 and Project
Professional 2013. You manage the implementation of a data warehouse.
You have set up your program master project with subprojects for each implementation area.
You need to make edits to the dependencies between projects.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution.
Choose two.)
A. View the subproject in Project Web App (PWA) and choose Edit. Then add your dependencies in
the predecessor's/successor's column.
B. Open the program-level project from Project Web App (PWA) by using Project Professional 2013.
Highlight the tasks you wish to link for a dependency with the control key. Then click the link button
on the tool bar.
C. Open the program-level project and the subproject from the Project Web App (PWA) and save
them to your local machine. Then add your predecessor's/successor's column in either file.
D. Open each of the required subprojects from the Project Web App (PWA) by using Project
Professional 2013 and create the link in the predecessor's/successor's column to the other projects
using the <>\Project Name\Task ID.
E. View the program-level project in Project Web App (PWA) and choose Edit. Then add your
dependencies in the predecessor's/ successor's column using the <>\Project Name\Task ID.
Answer: B,D
Microsoft test questions 74-344 certification training 74-344 demo 74-344 Actual Test
NO.2 A company deploys Project Server 2013 to perform a Portfolio Analysis, which they will use to
select the projects they will execute in the next fiscal period.
The company establishes the criteria to evaluate the portfolio components, and all business cases
must be evaluated under these parameters. When configuring Project Server 2013, the Project
Management Office (PMO) finds that the established criteria contain both qualitative and
quantitative elements, such as corporate reputation and internal rate of return (IRR).
You need to provide a system calculated approach to rank your strategic initiatives against each
other. Which two actions should you perform? (Each correct answer presents part of the solution.
Choose two.)
A. Create a Business Driver library that captures the criteria in quantifiable impact statements that
are specific and measurable.
B. Perform a pairwise analysis on the driver set to identify relative priorities.
C. Perform a prioritization by assigning a relative weight to each value criterion and establish the
priorities.
D. Create a custom field for each criterion and ensure each value is captured for each project by
making the project fields as required.
Answer: A,B
Microsoft practice test 74-344 test 74-344 Exam PDF 74-344 Free download 74-344 Dumps PDF
NO.3 Your organization is a multinational corporation that uses Project Online to plan and control
the projects in different business units. Each business unit has its own portfolio of projects but can
participate in strategic projects.
The Research and Development (R&D) department has been struggling to gather and materialize
the new ideas. The Project Management Office (PMO) has the necessary templates and Enterprise
Project Types (EPTs) to start a formal process for any new product and to adhere to the general
guidelines. However, the R&D group does not want to register all of their ideas since many are
related to improvements and few of them could be materialized into projects.
You need to generate a solution that allows R&D to gather their ideas and facilitate the
materialization into Enterprise Projects.
What should you do?
A. Create a new EPT for the SharePoint Task List and name it R&D New Idea.
B. Within the same site collection of Project Web App (PWA), create a Custom SharePoint Item List
for ideation and requests with custom fields that easily match with Project custom fields when using
the Add SharePoint Sites command in Project Center.
C. Create a new EPT for Enterprise Projects and name it R&D New Idea.
D. Within the same site collection of Project Web App (PWA), create a custom list for ideation and
match list columns with Project custom fields when using the Create Projects command in the
SharePoint Item List.
Answer: D
Microsoft exam prep 74-344 certification training 74-344 exam dumps 74-344 test answers 74-344
NO.4 Your organization is performing a Portfolio Analysis in Project Server 2013.
You want to create a consolidated Portfolio Analysis optimization based on Cost and Resource data,
which will be part of the project information in Project Server 2013.
You plan to provide different simulations to your organization by using those parameters and
returning the best prioritization.
This organization has two different unit directors, who have the final decision on the consolidated
Portfolio Analysis results.
You need to provide the ability for your unit directors to modify the final portfolio selection.
Which element should you use?
A. Resource Requirements
B. Project/Proposal Priority
C. Field Cost Constraint
D. Project Original Start
E. Field Force In/Out
Answer: E
Microsoft practice test 74-344 Free download 74-344 Bootcamp 74-344 Exam Tests 74-344
NO.5 You are a manager for a project your team has been working on for many weeks. Your project
is created as a Microsoft SharePoint task list project and is available in Project Center.
You have established the work breakdown structure (WBS), predecessors, assignments, and all of
the functionalities you can get from a SharePoint task list. However, the project has grown in detail,
and managing 200 activities has become difficult in Project Web App (PWA).
You need to ensure resources continue to report their progress in the same way.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution.
Choose two.)
A. Activate the Enterprise Project Features for the SharePoint site task list and edit the tasks in PWA
project details.
B. Edit the project in Project Professional 2013 from the Project Center by clicking the icon of the
SharePoint task list project in the Indicators column.
C. Activate the Enterprise Project Features for the SharePoint site task list and edit the tasks in
Project Professional 2013.
D. Edit the project in Project Professional 2013 by synching the SharePoint task list so you can take
advantage of the extended features.
Answer: B,D
Microsoft pdf 74-344 test 74-344 dumps 74-344 test answers
NO.6 Your organization uses Project Online for project portfolio selection. The business drivers and
priorities are set, as are the main constraints to identify the efficient frontier.
The company has been collecting business cases for new proposals in which many projects may
solve the same business need. For example, the selection for a Customer Relationship Management
system has six different proposals, whereas only one is necessary to fulfill the business need.
You need to guarantee that the analysis will produce the most viable proposal in terms of cost and
resources and that no repetitive efforts exist in the portfolio selection.
What should you do?
A. Create a mutual exclusion dependency among all these projects.
B. Create a mutual inclusion dependency among all these projects.
C. Exclude these projects from the Portfolio Analysis to prevent a deviation from the main goal.
D. Exclude the related projects from the portfolio after the cost analysis with the Force in/out option.
Answer: A
Microsoft 74-344 Test Answers 74-344 74-344 74-344 original questions
NO.7 Your work in a multinational corporation which uses Project Server 2013 to plan and control
projects in different business units. Each business unit has its own portfolio of projects but can
participate in strategic projects. The Project Management Office (PMO) has configured
Enterprise Project Types (EPTs) to create new products, launch marketing campaigns, and deploy
new lines of business tools to comply with the governance processes.
One of your roles is to identify new products. A local team in Singapore produces an effective idea
for a new product.
You need to create a business case for the next portfolio analysis. You need to gather general
information about the new product by efficiently collaborating with the local team.
What should you do?
A. Start a Project with the New Product EPT, which will trigger a workflow and allow you to display
and collect descriptive data and exchange information in the Project site.
B. Exchange information by sharing documents through SkyDrive Pro 2013.
C. Create a Team Site for the Singapore business unit for gathering information and assigning tasks.
Save the Team Site as a template for use within the New Product EPT.
D. Start a new enterprise project with the Microsoft SharePoint task list EPT, and grant immediate
access to the team so they can share information, assign tasks, and collaborate.
Answer: A
Microsoft 74-344 dumps 74-344 pdf 74-344 certification training 74-344 Test Answers
NO.8 You are a program manager for an organization that uses Project Server 2013.
You are responsible for implementing a data warehouse that compiles relational data from many
business areas. Your project managers need to be able to manage the implementation for a
business area as separate projects, while still recognizing the dependencies at a program level.
You need to maintain ownership and authority of key program dates at the program level.
What should you do?
A. Create one project file for all project managers that includes the program-level tasks and each
sub-project's tasks. Require each area project manager to share the file, and add their dependencies
within their own tasks.
B. Create and publish a master project file with general durations for each business area sub-project,
and have the area project manager reconcile the dates in their own project manually each week.
C. Have the project managers create, save, and publish sub-projects for each area. Then insert them
into a program-level project, define dependencies, and save and publish the program-level project
to the server.
D. Create a master project and insert your projects, but never publish the file on the server.
Answer: C